The renewal of the environmental clearance certificate involves the following additional activities for which a scoping plus assessment report and an updated environmental and social impact assessment (ESMP) are submitted:
- Extension of the solar park from 5 MWp to 100 MWp
- Battery extension from 5.9 MWh to 230 MWh
- 5 MW electrolyser (alkaline);
- The construction of an ammonia plant (4 mtpd);
- New utilities: Flare, Nitrogen Generation Unit, Water Treatment plant, and cooling water system.